[单选题]Schedule compression shortens the project schedule without changing the project scope, to meet schedule constraints, imposed dates, or other schedule objectives. Schedule compression techniques include crashing and ( ).
  • Afast tracking
  • Bwhat-if scenario analysis
  • Cresource leveling
  • Dcritical chain method