[单选题]Schedule compression shortens the project schedule without changing the project scope, to meet schedule constraints, imposed dates, or other schedule objectives. Schedule compression techniques include crashing and ( ).
Afast tracking
Bwhat-if scenario analysis
Cresource leveling
Dcritical chain method