[单选题]Earned value management (EVM) integrates the scope baseline with the ( ) baseline, along with schedule baseline,to form the performance baseline, which helps the project management team assess and measure project performance and progress.
  • Aquality
  • Brisk
  • Cchange
  • Dcost