[单选题]If the approved change requests have an effect on the project scope, then the corresponding component documents and cost baselines, and( ) of the project management plan are revised and reissued to reflect the approved changes。
  • Adeveloping baselines
  • Btesting baselines
  • Cschedule baselines
  • Dending baselines